1. Worked with the Brewer Water Department on a
second interconnect
between the two
water systems. These interconnects allow a short-term
emergency supply of water to be fed in either direction.
2. Completed the
construction of a 3.4 million
gallon reinforced concrete water storage tank at Essex St. This
concrete tank replaces two old steel tanks that needed
repairs and painting. The concrete
storage tank does not need repainting and has significantly
lower long-term maintenance costs. New technology allows
construction of larger concrete storage facilities than
previously possible.
3. Started preliminary
design for installation of federally mandated additional
water treatment (ultra-violet disinfection) at
the Butler Ozone Plant by 2013, at an estimated cost of $6
million. (The alternative to UV disinfection could be
construction of a filter plant at a cost of $65 million).
4.
Began design
of overdue upgrades for Johnston Pump Station which has essentially
been on-line since 1957. The upgrades would substantially
increase electrical efficiency.
5.
Finalized plans to install an electric power-generating turbine
producing “green power” at BWD’s
control valve site in Veazie. One pressure-reducing valve was replaced with the turbine,
and the resulting power will be sold.
6.
Complied
with a state-mandated conversion of our records related to water
lines and valves to an electronic (GIS) format. The new
format—which can be shared with others such as the City of
Bangor—will provide a more in-depth, better organized, and
easier to use database.
7. Replaced
approximately 1200 feet of 8-inch pipe on Mt. Hope Ave. between
Forest Ave. and Birch St. and 600 feet of 6-inch pipe on
Bellevue Ave. Both locations had old water pipes that had
experienced several leaks.
8. Infrastructure
maintenance of hydrants and valves: targeted older hydrants and
inoperable valves.