|
SECTION
1 - Water Main Construction
A.
Description (Return to
Table of Contents)
This document addresses: excavation and backfill of the trench;
furnishing, and installing cement-lined ductile iron pipe, valves,
fittings, hydrants, and accessories of the types and classes described
herein and shown on the plans; making connections to the existing public
water supply system; pressure testing and disinfecting the completed
installation; and incidental work as described herein.
Please
refer to the Bangor Water District Standard Details for detailed
drawings of the following items:
Air
Relief Valve Installation
Typical Trench Detail
Typical Trench Detail in Ledge
Residential Meter and Backflow Installation
Commercial Meter and Backflow Installation
Thrust Block Specifications
Hanging Thrust Block Installation
Restraining C-900 Pipe
Typical Main Tie-in to an Existing Main
Typical Domestic / Fire Service Installation
Fire Service Penetrations Through Walls and Under Wall Footings
Typical Domestic Service Connection
Hydrant Installation
Offset Installation
Permanent Style 2 inch Blow Off Installation
B.
Excavation (Return to
Table of Contents)
All pipe shall be installed with a minimum five (5) foot depth
of cover over the top of the pipe. Where existing or proposed pipes,
conduits, culverts, cables, wires, etc. interfere with laying at this
depth, the water pipe shall be laid at greater depth to clear the
obstruction by at least twelve (12) inches, where practical.
Excavation
shall be kept free of water and special precautions shall be taken to
prevent entry of water, mud or other foreign substances into the line.
Temporary caps shall be installed over all openings at the end of each
day, when the work is suspended for periods of 30 minutes or more
(including lunch hours), or whenever necessary to protect the work in
progress.
Pipes
shall be carefully lowered into the excavation, be guided into proper
position, and joined to the preceding length or fitting. Suitable
excavated material (i.e. free of stones and capable of being properly
compacted) or borrow shall be placed and tamped under and around the
pipe, taking care to maintain equal depth on both sides and to prevent
movement of the pipe from its proper alignment. Where directed by the
District, due to soft or otherwise unsuitable bottom conditions, pipe
bedding shall be placed in accordance with the requirements of BWD
standard details.
All
excavated areas shall be adequately shored and braced so that the earth
will not slide or settle, and so that all existing improvements of any
kind will be duly protected from damage. All damage resulting from
inadequate bracing or shoring will be the responsibility of the
Contractor. The Contractor shall make all necessary repairs and do
reconstruction at his/her own expense. S/he will bear all other expenses
resulting from any such damage due to lack of adequate shoring.
The
Contractor will take special precautions on those projects that are near
road curbs. Every effort shall be made to avoid disturbing any roadside
curbing. Should it become necessary to disturb or remove curbing during
water main installation, the Contractor shall, at his/her own expense,
replace such curbing in accordance with construction practices in the
latest edition of the Maine Dept. of Transportation Highway
Specifications or local town specifications.
The
Contractor shall note that in some areas underground sewer mains and
services, storm drains, telephone or communications cables, gas lines,
and other below-ground utilities may exist in close proximity to the
work. Excavation around other utilities, pipes, culverts, and similar
installations shall be done with extreme care. It shall be the
Contractor's responsibility to contact the owner/operator of each
utility to be encountered and obtain information relative to location
and depth before excavating in the area. It shall be the contractor's
responsibility to comply with the State of Maine "Dig Safe"
law. The Contractor shall promptly notify the Utility Owner concerned in
the event of damage occurring during construction, whether caused by
him/her or others.
The
Contractor shall use extra caution to avoid disturbing any water service
connections along the proposed water main routes. Any disruption of
water service or any damage to such service lines shall be immediately
reported to the District and the property owner. It shall be the
Contractor's responsibility to immediately repair any damage done to
water services during installation of new water mains.
In
the event that underground utilities conflict with the location of the
work, the Contractor shall promptly notify the District and shall not
disturb the conflicting utility until given specific instruction
specifying the action to be taken.
Private
utilities (building drains, etc.) encountered in the work shall be
brought to the attention of the District and be handled in such manner
as he directs.
Suitable
material from excavation shall be used to the maximum extent possible in
grading over and adjacent to the pipe and in filling adjacent low land
as directed by the District. Materials that cannot be so placed shall be
removed as directed by the District.
No
separate payment will be made for excavation including labor, materials,
and use of equipment and tools necessary to complete the excavation
work. All materials used and work performed for excavation will be
considered as incidental to other items of these specifications.
On
portions of the project which are within the confines of an existing
roadway, the Contractor shall provide for at least one-way traffic at
all times with special regard for the safety of the traveling public.
Traffic control shall be accomplished in accordance with M.D.O.T.
specifications and shall be coordinated with the local Town Public
Safety office.
Property
owners whose driveways will be blocked for a short period of time will
be notified 24 hours and one hour in advance of the excavation so that
vehicles can be removed when necessary. Driveways shall not be blocked
at night without the expressed consent of the property owner.
C.
Test Pit Excavation (Return
to Table of Contents)
At such locations as may be determined by the District, the
Contractor shall perform excavation to locate various subsurface
utilities. The limits and depth of such excavations shall be determined
by the District, and the Contractor shall perform all work as directed
by the District. In addition, the Contractor shall carefully backfill
the trench, using twelve (12) inch compacted layers, and restore the
surface to a condition equal to or better than it was before.
D.
Extra Earth Excavation (Return
to Table of Contents)
Where necessary during construction, the Contractor shall perform
extra excavation where the District so directs. The following conditions
may result in the Contractor performing extra excavation:
1.
Necessity of installing water mains below other subsurface utilities
2.
Discovery of unsuitable material in the trench bottom
3.
Necessity of widening the trench beyond specified limits in order to
remove or relocate structure/(s) encountered during construction
E.
Blasting (Return to Table of
Contents)
The District has adopted the blasting requirements used by the City
of Bangor. The Contractor must obtain a blasting permit from the City,
which includes a pre-blast survey per City specifications.
The
Contractor shall employ an experienced blaster and shall comply with all
laws, ordinances, and applicable safety codes and regulations relative
to the handling, storage, and use of explosives and protection of life
and property. The Contractor shall be fully responsible for all damage
thereto caused by his/her blasting operations. Signals warning persons
of danger shall be given before every blast. Suitable weighted timer
mats, wire rope mats, or other approved covering shall be provided to
confine all materials lifted by blasting within the limits of the trench
or excavation.
The
excavated ledge material may be used in approved areas for backfilling
the top half of the trench except that stone fragment exceeding the size
of one cubic foot shall not be used in the backfill.
F.
Excavated Material (Return to
Table of Contents)
All excavated material shall be placed in a manner that will not
endanger the work and will avoid obstructing sidewalks and driveways.
Gutters and other means for providing surface drainage shall be kept
clear at all times.
G.
Preparation of Water Line Trench Bottom (Return
to Table of Contents)
Pipe shall be laid directly on the trench bottom.
H.
Shaping Trench Bottom (Return
to Table of Contents)
Prior to lowering pipe into the trench, the trench bottom shall be
made flat and cut true and even to grade so as to provide continuous
contact of the trench bottom with the pipe.
I.
Unsuitable Conditions (Return
to Table of Contents)
No pipe shall be laid in wet trench conditions, which
preclude proper bedding, on frozen trench bottom, or when, in the
opinion of the District, the trench conditions or the weather are
unsuitable for proper installation.
J.
Cutting Pipe (Return to
Table of Contents)
All cutting of iron pipe shall be done using an electrically,
pneumatically, or gasoline operated machine. Blades shall be carbide
tipped for cutting cement-lined iron pipe or abrasive type for proper
material being cut. The machine used shall be portable saw equal to
those made by Fein, Wache, or Homelite, or approved equal. When the cut
end is to be used as a "Bell-Tite" or "Tyton" joint,
it shall be tapered back on the outside of the cut about l/8-inch, at an
angle of about 30 degrees with the pipe center. This shall be done with
a course file or portable grinder.
K.
Connection to Existing Water Main (Return
to Table of Contents)
The Contractor shall locate and confirm sizes and materials of
existing mains, excavate, furnish and install tapping sleeves and
valves, and backfill the excavation. All materials, including mechanical
joint accessories, valve boxes, and other items necessary to make all
joints watertight and provide complete and effective connections to
existing water mains shall be provided by the Contractor. All tapping
sleeves shall be pressure tested prior to BWD tapping the main.
No
valves on existing mains shall be operated by the Contractor without the
permission of the Bangor Water District. The location of the points of
connection and the locations of the existing mains are approximate only,
and the Contractor shall provide all labor, equipment and material for
all connections which shall be included in the Unit Bid price for
tapping sleeves with valves.
All
size on size taps shall be done with full body tapping sleeves meting
BWD material specifications.
L.
Thrust Backing, Anchorage, and Joint Restraint Water Line Fittings
(Return to Table of Contents)
Thrust backing and anchorage is required wherever the pipe: a)
changes direction as at tees, bends, crosses, and tapping sleeves; b)
changes sizes, as at reducers; or c) stops, as at dead ends and
hydrants.
Concrete
shall be used for thrust blocks, and they shall be poured in place or
pre-cast in accordance with BWD standard details. Poured in place thrust
blocks shall be constructed by pouring concrete between the fitting and
the undisturbed wall of the trench. A dry mixture shall be used so that
the concrete may be easily shaped into the desired form, a wedge with
the wide end against the solid wall. Care shall be exercised to ensure
that the concrete is clear of joint accessories, bolts, nuts, and
flanges.
The
Contractor shall furnish and install all materials and equipment, and
perform all labor for the manufacture, transporting, placing, curing,
and testing concrete for thrust blocks. Concrete shall be composed of
Portland cement, water, fine and coarse aggregate, and an air-entraining
mixture. Accelerating or anti-freeze admixtures will not be permitted.
Cement shall be Type II confirming to ASTM Cl50 or ASTM Cl75.
Aggregates
shall conform to ASTM C33. For thrust blocks, all aggregates shall be
able to pass through a screen with two (2) inch square openings.
Preferably,
water used in mixing and curing concrete shall be potable. Non-potable
water shall be fresh, clean and free from injurious amounts of sewage,
oil, acid, alkali, salt, or organic matter.
Air
entraining admixtures shall conform to the Specifications for Air
Entraining Admixtures for Concrete (ASTM C260).
Unless
otherwise shown on drawings, concrete used for thrust blocks shall have
a 28-day compressive strength of 2,500 psi. When no preliminary strength
tests of the concrete to be used are made, the water-cement ratio shall
not exceed the following values.
|
Specified
Compressive
Strength at 28 days
|
Maximum
permissible water-cement ratio, lb.
of water per lb. of cement
|
|
2,000
|
0.70
|
|
2,500
|
0.55
|
|
3,000
|
0.46
|
|
3,500
|
0.40
|
|
4,000
|
0.35
|
Water-to-cement
ratios other than the above may be used when the strengths of the
concrete are to be established by tests. The District shall determine if
concrete testing is necessary and shall also determine the method of any
concrete testing which is performed. The slump of concrete for thrust
blocks shall be the minimum that is practicable such that the concrete
may be easily shaped into the desired form, a wedge with the wide end
against the solid undisturbed wall. Segregation of materials in the
mixture shall not be permitted. Forming and placing of concrete for
thrust blocks shall be done under the direction of the District.
Curing
and form removal for concrete thrust blocks, and requirements due to air
temperature and weather conditions shall follow proper construction
practices and shall be subject to approval by the District.
Minimum
thrust block area against the undisturbed trench wall shall be as
follows:
|
Pipe
Size
|
Fitting
or Pipe Change
|
Minimum
thrust block
area against undisturbed
earth (square feet)
|
|
6"
|
90
degrees
|
5.5
|
|
6"
|
11
1/4 degrees
|
1.5
|
|
6"
|
Dead
end
|
6.5
|
|
8"
|
90
degree bend
|
6.5
|
|
8"
|
45
degree bend
|
5.0
|
|
12"
|
90
degree bend
|
20.0
|
|
12"
|
11
1/4 degree bend
|
4.5
|
|
12"
|
Dead
end
|
22.0
|
|
8"
|
90
degree bend
|
6.5
|
|
8"
|
45
degree bend
|
5.0
|
|
12"
|
90
degree bend
|
20.0
|
|
12"
|
11
1/4 degree bend
|
4.5
|
|
12"
|
Dead
end
|
22.0
|
|
16"
|
22
1/2 degree bend
|
9.5
|
|
16"
|
90
degree bend
|
23.5
|
|
20"
|
Dead
end
|
41.0
|
|
12x12"
|
Tapping
sleeve
|
14.0
|
|
8x8"
|
Tapping
sleeve
|
9.5
|
|
6x6"
|
Tapping
sleeve
|
8.5
|
|
|
Hydrants
|
5.5
|
|
16x16x16
|
|
8.5
|
|
16x16x8
|
|
9.5
|
|
16x16x12
|
|
14.0
|
|
20x20x6
20x20x16
12x12x6
|
|
8.5
26.5
8.5
|
In
addition to the above requirements for thrust backing, water mains shall
be protected from movement by thrust forces in the following manner:
1.
All fittings, valves, hydrants, and caps shall have ductile iron
standard glands, unless otherwise directed by the District.
2.
All push-on joints in hydrant lateral shall be secured by rods as shown
on the contract drawings or as directed by the District.
3.
All valves shall be rodded to the tee.
Bolts
on all ductile standard glands shall be systematically tightened with a
torque wrench according to the manufacturer's requirements. When all
bolts have been tightened in this manner, each bolt shall be retightened
according to manufacturer's requirements in the event that some may have
loosened during the initial tightening process.
When
a fitting is used to make a vertical bend, anchor the fitting to a
thrust block braced against undisturbed soil. The thrust block should
have enough resistance to withstand upward and outward thrusts at the
fitting.
All
services, domestic and fire protection, must have separate shut-off
valves.
SECTION
2 - Materials (Return
to Table of Contents)
Refer
to the District's Materials
Specifications for information.
SECTION
3 - Water Line Testing (Return
to Table of Contents)
A.
Water line testing shall be done in accordance with AWWA specifications.
1. Chlorination shall be done in accordance with ANSI/AWWA C651-92, the
AWWA standard for Disinfecting Water Mains Section 5.2, Continuous-Feed
Method.
2. Integrity of the installed pipeline shall be confirmed using ANSI/AWWA
C600-93, the AWWA standard for Installation of Ductile-Iron Water Mains
and Their Appurtenances.
B.
Sewer Line Crossings (Return
to Table of Contents)
Where the water main extensions cross a sewer line or house lateral,
the water main joints shall be spaced such that no water main joint is
closer than ten (10) feet to the sewer centerline. When possible, the
water line shall be deflected such that it passes eighteen (18) inches
over the sewer.
SECTION
4 - Common Borrow, Roadway Gravel, and Pipe Bedding
A.
Description (Return to Table
of Contents)
Furnish and place common borrow where trench material is unsuitable,
gravel for drives, and parking areas, and granular pipe bedding as
directed by the District at locations where the existing soil conditions
are unsuitable.
B.
Common Borrow (Return to Table
of Contents)
Borrow material shall contain no rocks or fragments with dimensions
in excess of the layer thickness being placed, and shall be free of
frozen earth, ice, snow, rubbish, peat and other unsuitable material.
Borrow shall not be used in the work when suitable materials from the
excavation is available.
Common
borrow shall be placed in (12) twelve inch layers and be thoroughly
compacted before the next layer is placed.
C.
Roadway Gravel (Return to
Table of Contents)
Furnish and place gravel to a depth of fifteen (15) inches for
access drives and parking areas, and to a depth equal to the depth of
existing gravel base in excavation made in existing roadways. Roadway
gravel to be furnished under this item shall be composed of sound
durable rock together with fine material. All material shall pass a
screen having a three (3) inch square opening and not more than fifty
(50) percent of all material shall pass a quarter-inch (1/4) opening.
The gravel shall be reasonably uniform in grading and contain not more
than five (5) percent of weight of combined organic material and clay.
Gravel
shall be placed in twelve (12) inch layers and be thoroughly compacted
before the next layer is placed.
D.
Pipe Bedding (Return to
Table of Contents)
Shall
be as per BWD Standard Details
E.
Trench Backfill (Return to
Table of Contents)
Shall
be as per BWD Standard details.
Where
flowable fill is required per the Maine Dept. of Transportation or local
town standards, placement of sand or stone around pipe to a depth of 1
foot above top of pipe must occur prior to placement of flowable fill.
SECTION
5 - Hot Bituminous and Concrete Pavement
A.
Description (Return to Table of
Contents)
Furnish
and install bituminous surface material for the replacement of all
drive, parking area, and street pavements removed to facilitate
construction of the water main and appurtenances. It is the intent that
removed street surfaces and pavements be reconstructed to a quality
equal to or better than that which existed prior to the opening of the
street for construction purposes. The completed pavement shall have a
minimum thickness of three (3) inches and match the thickness of the
original pavement whenever it is greater.
The
bituminous material used shall conform to specifications for an
acceptable mixture in accordance with the Maine State Highway
Specifications for binder and wearing courses, except as modified or
supplemented herein.
The
bituminous surface material shall be placed in layers that will yield a
finished binder course of two (2) inches and wearing course of one (l)
inch, hand spread and raked, and then rolled. The wearing course shall
be finished one-fourth (l/4) inch higher than the existing pavement.
During
the progress of the work, the maximum distance from the point of pipe
laying to the replaced binder course shall be two hundred (200) feet,
unless otherwise authorized by the District. During weekends, the binder
course shall be installed up the point of pipelaying.
Placement
of the wearing course shall begin within three (3) days after completion
of water main construction operations within the roadway.
Temporary
paving with a finished minimum depth of one-and-a-half inches (1 1/2)
inches shall be placed in the areas of roadway designated by the
District.
In
some areas of water main construction, it may be necessary to replace
reinforced concrete pavement. Should the District require the
replacement of reinforced concrete pavement, the Contractor shall
replace disturbed areas with new concrete at least four (4) inches
greater in depth than the existing concrete pavement and the new
concrete surface shall be graded to match the existing surface.
B.
Paving Time Limits (Return to
Table of Contents)
The
Contractor shall be responsible for all conditions set forth under the
City of Bangor Street Opening Permit. Under conditions of this permit,
no paving shall be allowed after winter shutdown (approximately Dec. l),
and all roads must be satisfactorily paved before winter shutdown. The
Contractor shall be responsible for maintaining any paving done through
project duration, especially during winter shutdown.
SECTION
6 - Loam, Seeding and Sodding
A.
Description (Return to Table
of Contents)
This item shall consist of furnishing and placing loam, seed, and
sod as called for on the plans, or as authorized.
B.
Materials (Return to
Table of Contents)
Loam:
Two inches of loam shall be placed in accordance with BWD standard
details. The loam shall be of an approved quality topsoil. It shall be
free from gravel, roots, clods, stones, and other material, which would
tend to form air pockets in the soil. The use of sour loam or mulch will
not be permitted. Prior to stripping the loam, the Contractor will
remove grass, briar, stumps or roots by mowing, grubbing, or other
satisfactory means.
Fertilizer:
Commercial fertilizer for seeding shall be l0-l0-l0 grade containing at
least ten (l0) percent available nitrogen, ten (l0) percent readily
available phosphoric acid and ten (l0) percent total available potash.
The fertilizer shall be supplied in unopened bags with the weight,
contents, and guaranteed analysis shown thereon or on a securely
attached bag.
Seed:
All seed shall be certified as to mixture germination and purity, as
being in conformity with the following requirements. All seeds shall be
from the previous year's crop. Each type of seed shall have a percentage
of germination not less than eighty-five (85) and shall have not more
than one (l) percent weed content.
The
seed mixture shall consist of seeds proportioned by weight as follows:
|
Kentucky
Blue Grass
|
50%
|
|
Red
Top
|
25%
|
|
Canada
Blue Grass
|
10%
|
|
Dwarf
White Clover
|
10%
|
|
English
Rye Grass
|
5%
|
Sod:
Sod shall, in general, be obtained from sources having soils of the same
type as the base soil over which it is to be placed, except that sod
from light sandy soils will not be acceptable. The sod to be placed upon
sandy soils shall be of such character and moisture content that the sod
will not break up or crumble during the operations of cutting,
transporting, or laying. All sod shall be approved in its original
location before cutting. The sod shall consist of a dense, well-rooted
growth of perennial and desirable grasses, indigenous to the general
locality where it is used and shall be free of noxious weeds.
Wood
pegs shall have a minimum cross-section area of one (1) square inch and
a minimum length of twelve (12) inches.
C.
Construction Methods (Return
to Table of Contents)
1.
Loam
All
slopes and other areas where loam is required shall be trimmed and
shaped to the required sub-grade of the area. Before placing the loam,
the prepared areas shall be scarified or loosened to a depth of at least
two (2) inches by harrows, pulveriziers, or other means.
Loam
shall be spread on the prepared areas to the uniform depth shown on the
plans or as directed. After spreading, all existing lumps or clods shall
be broken up and all rocks over two (2) inches in diameter, and roots,
litter or foreign matter shall be raked up and disposed of. When the
loamed area is to be seeded and is also adjacent to an existing lawn,
all rocks over one (l) inch in size shall be removed by raking or by
other approved methods, and the material shall be compacted by rolling
with a suitable lawn roller. All compacted loamed surfaces shall conform
to the required grades and cross sections.
When
loam is spread, upon which the sod is to be placed, the material shall
be spread to the required depth. Rocks exceeding two (2) inches shall be
raked up, together with undesirable roots and debris, and disposed of.
The loam need be only roughly shaped since in placing the sod, the
material shall be adjusted to give the desired finished elevation and
cross section of the sod surface. Any excess of loam remaining in stock
piles, after completion of loaming all required areas, shall be trimmed
or leveled to present a neat appearance as directed.
2.
Fertilizing
After
the areas to be seeded have been loamed and brought to grade, the soil
shall be brought to a friable condition by harrowing or otherwise
loosening and mixing it to a depth of at least four (4) inches before
fertilizing. The commercial fertilizer shall be applied to the soil by
means of a mechanical spreader or other approved method which is capable
of maintaining a uniform rate of application. The fertilizer (l0-l0-l0)
shall be applied at the rate of twenty-five (25) pounds over one
thousand (l,000) square feet of area. When other commercial fertilizers
are used as authorized above, the application shall provide a minimum
amount of the basic ingredients as specified for the l0-l0-l0
fertilizer. Fertilizer shall be thoroughly harrowed, raked, or otherwise
mixed satisfactorily with the soil to a depth of not less than one (l)
inch. Fertilizing shall be done when the soil is in a moist condition
and at last twenty-four (24) hours before sowing the seed.
3.
Seeding
Grass
seeds of the required mixture and quality shall be sown by a mechanical
seeder or other method, which will sow a uniform quantity as required
over the whole area to be seeded. The mechanical seeder shall be capable
of being operated to avoid the growth of grass in rows. The application
of the seed shall be in the amount of three pounds per one thousand
(l,000) square feet. Seeding shall be done when the air is calm, and
between the dates of April l5 - October 1.
After
seeding all areas shall be lightly raked by hand to mix the seed and
loam, and to smooth the surface. Lawn areas shall then be rolled with a
light lawn roller.
When
dry periods occur during the allowable dates for seeding, the Contractor
shall apply sufficient water to the area to satisfactorily maintain the
moisture content of the soil to allow proper germination of the seed and
growth of the grass.
4.
Sodding
The
sod bed or area from which the sod is to be cut shall be mowed at least
twice before the sod cutting begins. Mowing shall be by means of lawn
mowers or other approved equipment at intervals of one week between
mowings. Cutting of sod shall not be started until at least one week
after the second mowing. The sod shall be cut in strips having a minimum
width of twelve (12) inches and length of not less than eighteen (18)
inches. The sod shall be cut to uniform thickness of not less than two
(2) inches.
The
sod shall be freshly cut by means of an acceptable sod cutter and
transported to the area to be sodded in an unbroken condition. Storage
of sod will not be permitted and it shall be placed in final position
immediately after cutting. Sod shall be loaded and unloaded by hand.
The
sod shall be moist and shall be laid on a moist bed of loose loam. The
sod shall be carefully placed by hand in rows at right angles to the
slopes, commencing at the base of the area to be sodded and working
upward.
The
bottom edges of sodded areas shall extend at least two inches into the
ground or ditch bottom. All other edges of sodded areas shall be turned
into the ground and covered with a layer of top-soil at least two (2)
inches in depth, which shall be thoroughly compacted to conduct the
surface water over the edge of the sod.
The
transverse joints of sod strips shall be broken and the sod carefully
lain to produce tight joints. Any spaces left between sod strips shall
be filled with loam. Where the sod may be displaced during sodding
operation, the workmen shall work from ladders or treaded planks. The
sod shall be firmly compacted by tamping with an approved tamper
immediately after a workable area has been placed.
After
tamping, the sod surface shall present a smooth, even surface free from
bumps and depressions, and true-to-line grade and cross section. On
slopes steeper than three horizontal to one vertical, the sod shall be
pegged with wooden pegs. The pegs shall be spaced not more than two (2)
feet apart in any direction, and shall be driven flush with the surface
of the sod.
During
July and August, and during periods of drought, the Contractor may place
sod only if he will satisfactorily water the sod and ensure continued
growth of the grasses. Sod placed during such time and not surviving
shall be removed and replaced by the Contractor at his expense.
Frozen
sod shall not be used, nor shall sod be placed upon frozen ground.
SECTION
7 - Permits (Return
to Table of Contents)
A Highway Opening Permit must be obtained from the City of
Bangor and the Maine Dept. of Transportation before any excavation is
made within the right-of-way of state, state-aid and City roads. The
Contractor must obtain this permit, and the permit fees must be paid at
the time of application, which will occur prior to the actual start of
the work.
The
contractor is responsible for signing for service from BWD and paying
all applicable fees and/or deposits prior to BWD commencing work,
including fire service agreements and main extension agreements. |